JUST IN: National Grid Restored After Temporary Blackout

The Transmission Company of Nigeria (TCN), says the national grid has been restored after experiencing a temporary disturbance at about 8:15 a.m. on Saturday.


TCN’s General Manager for Public Affairs, Mrs Ndidi Mbah, disclosed this in a statement in Abuja on Saturday.

Mbah said that TCN engineers at Jebba successfully carried out switchings by isolating the faulty current transformer.

She stated that the engineers had also reconfigured the busbar arrangement, restoring the power supply to the station and other parts of the grid.


Mbah reported that according to the information from the National Control Centre (NCC), the bus section of a current transformer exploded at the 330kV Jebba Transmission Substation.

“As expected, the protection system was activated, which promptly opened the busbars to curtail the explosion, thereby preventing the outbreak of fire and further damage to adjacent equipment.

“The action of the protection system led to a temporary disturbance on the grid,” she explained.

Edited By: Manasseh Paul-Worika

The journey to greatness is one step at a time and you should be part of it.

Join the NDconnect community channels on WhatsApp and Telegram to get News updates and add to the voices shaping the future : ❤️

WhatsApp Channel: https://whatsapp.com/channel/0029VajWDeK29754T7BzHU2H

WhatsApp Community: https://chat.whatsapp.com/Dlm6LmlgmzaKCMUYP4BPwC

Telegram t.me/NDConnectNewsAlert